The project of the Elefsina – Stavros – Spata Airport motorway & Western Ymittos Peripheral road (commonly called \”Attiki Odos\”) is one of the most important and complex infrastructure projects iimplemented in Greece. The total budget of the Attiki Odos project amounts to 2,94 billion € and is implemented and it is funded by the Concessionaire own capital, the Greek State, the European Investment Bank and an International Group of Commercial Banks, under a D.B.F.O.T. contract (Design, Built, Finance, Operate, Transfer). Doxiadis Associates in cooperation with Halcrow Technical Consultant provided for five years TA services to the International Group of Commercial Banks funded the Attiki Odos project.

  • Total length 72,7 km (45,2 km. of six lane motorway, 18 km. of four lane motorway and 9,5 km. four lane road \\\”artery\\\” class).
  • 32 grade separated junctions, 22 major road bridges, 77 local road overpasses, 17 local road underpasses, 31 large – scale culvert structures, 4,5 km. of tunnels, 63,2 km. of retaining walls, 4 main motorway toll stations, 32 side toll stations